IDK Meeting on North Pipeline's Solar Energy Project Scheduled for January 6th
The Environmental Impact Assessment (EIA) meeting regarding the Solar Power Plant project with a capacity of 10 MWe/12,980 MWm, planned to be carried out by Kuzey Boru, will be held on January 6.
In a statement on the website of the General Directorate of Environmental Impact Assessment Permit and Audit, the following information was provided:
"The EIA Report prepared for the Solar Power Plant project with a capacity of 10 MWe/12,980 MWm (11.532768 ha), planned to be carried out by Kuzey Boru A.Ş. within the borders of Harran district in Şanlıurfa province, has been submitted to our Ministry in accordance with Article 11 of the EIA Regulation, and the review and evaluation process has begun. An EIA meeting will be held on 01/06/2025 regarding the project. The EIA Report submitted to our Ministry is available at https://eced-duyuru.csb.gov.tr/eced-prod/duyurular.xhtml."